{"ai_json_enabled":true,"answer":"Define the evidence for each milestone in the contract before construction starts. The wording should make clear what work must be finished, which approved drawings or specifications apply, and what documents or inspection findings demonstrate completion. Depending on the stage, evidence may include dated site photographs, progress reports, relevant approvals, and an inspection by an independent qualified professional. A photo update alone may not establish that concealed work or technical requirements are satisfactory. Arrange for the inspector to report in writing and identify any incomplete or defective work. The contract should say who may inspect, how much notice is required, how findings are addressed, and whether payment is withheld until agreed corrections are made. Keep payment records and match each transfer to the corresponding milestone and supporting documents. Have an independent Thai lawyer and suitable technical adviser review the proposed evidence and payment wording before signing; the appropriate checks depend on the project and contract.","answer_source":"openai_conversational_breadcrumb","category":"Building & Renovating in Khao Lak","category_slug":"building-in-khao-lak","confidence":"grounded_in_approved_property_guide_context","conversation_depth":2,"conversation_followup_type":"evidence","conversation_parent_slug":"which-milestones-are-most-important-to-protect-payment-timing","conversation_reason":"The parent says milestones should be independently verifiable, prompting a practical question about what evidence actually supports release of payment.","conversation_root_slug":"how-should-an-off-plan-villa-payment-schedule-be-structured","created_at":"2026-11-21T19:30:14+00:00","daily_publish_cap":3,"date_published":"2026-11-22","display_date":"2026-11-22","drip_batch":"2026-11-22","drip_status":"daily_auto_published","freshness_warning":"Property prices, availability, construction progress, rental rules and legal requirements can change. Confirm current details with the developer, seller, property manager, Thai lawyer or qualified adviser.","id":"daily-20261122-02-13a9915a30","image_ids":["[\"klpg_img_0181\"","\"klpg_img_0366\"","\"klpg_img_0375\"","\"klpg_img_0378\"","\"klpg_img_0379\"]"],"json_url":"/answer/what-proof-should-i-require-before-agreeing-that-a-construction-milestone-is-complete.json","last_updated":"2026-11-21T19:30:14+00:00","public_disclaimer":"This is general property guide information only, not legal, tax, financial or investment advice. Confirm the current position before signing documents or transferring funds.","publish_status":"published","published_at":"2026-11-21T19:30:14+00:00","question":"What proof should I require before agreeing that a construction milestone is complete?","question_intent":"evidence","rss_enabled":true,"rss_pub_date":"Sat, 21 Nov 2026 19:30:14 GMT","schema_enabled":true,"site_key":"khao-lak-property-guide","slug":"what-proof-should-i-require-before-agreeing-that-a-construction-milestone-is-complete","source":"daily_auto_digital_twin_property_guide","source_record_ids":[],"source_type":"daily_auto_digital_twin_property_guide","source_urls":[],"status":"published","tags":["conversation follow-up","daily_property_guide","Building & Renovating in Khao Lak","daily_auto","digital_twin"],"updated_at":"2026-11-21T19:30:14+00:00"}